One of the strengths of Kinkaid Civil Construction is the depth and variety of experience we possess, both in scope and the locations where we work.  Each project, regardless of delivery method, is built utilizing our “Partnering Approach”.   Our partnering approach is successful when all project stakeholders are communicated with both consistently and openly along with being treated fairly.

 

Miami : Phase 2 Wastewater Collection

Role: Prime Contractor Owner: Town of Miami Contract Amount: $4,714,244 Duration: 7 months Scope: 21,200 LF of sewer installation (8"-16") 414 LF of jack & bore under US-60 and UPRR highway 239 sewer service installations 112 sewer manhole installations 2,082 LF of...

read more

Plevna, MT Waterline

Role: Prime Contractor Owner: Town of Plevna Contract Amount: $2,059,430 Duration: 5 months Scope: 14,373 LF of waterline installation (6") 582 LF of jack & bore under Highway 12 102 water service installations 890 SY of asphalt removal/replacement 17,240 SY of gravel...

read more

Buckeye Reclaimed Waterline

Role: Subcontractor Contract Amount: $1,625,879 Duration: 6 months Scope: 18,775 LF of waterline installation (2"-12")   Site grading for water tanks   1274 SY of asphalt removal/replacement   3919 SF of concrete removal/replacement      ...

read more

Marana – Tangerine Sewer Conveyance System

Role: Prime Contractor Owner: Town of Marana Contract Amount: $2,095,288 Duration: 6 months Scope: 18,170 LF of sewer line installation (15"-18") 45 sewer manhole installations 7 CMID irrigation canal improvements 862 SY of asphalt removal/replacement 1890 SF of...

read more

Yuma P-535 Hangar

Role: Subcontractor Contract Amount: $1,290,407 Duration: 27 months Scope: 1054 LF of waterline installation (3"-12") 1422 LF of sewer line installation (4"-18") 12 sewer manhole installations 1 lift station installation 1158 LF of storm drain installation (8"-24") 29...

read more

Apache Junction Water District

Role: Prime Contractor Owner: Apache Junction Water District Contract Amount: $448, 413 Duration: 4 months Scope: 2636 LF of waterline installation (12") 22 water service installations 827 SY of asphalt...

read more

East Valley Commerce

Role: Subcontractor Contract Amount: $868,716 Duration: 3 months Scope: 4750 LF of waterline installation (3"-12") 1722 LF of sewer line installation (6"-8") 6 sewer manhole 4000 LF of storm drain installation (12"-120") 25 storm drain catch basin...

read more

Metro-Chandler Airport Center

Role: Subcontractor Contract Amount: $881,613 Duration: 3 months Scope: 1235 LF of waterline installation (3"-8") 230 LF of sewer line installation 4004 LF of storm drain installation (12"-96") 34 storm drain manhole & catch basin...

read more

Buckeye Business Center

Role: Subcontractor Contract Amount: $1,015,464 Duration: 20 months Scope: 6990 LF of waterline installation (3"-12") 3580 LF of offsite waterline installation (12") 3030 LF of sewer line installation (3"-8") 1 life station 460 LF of storm drain installation (12"-18")...

read more

Tempe Gardens Waterline

Role: Prime Contractor Owner: City of Tempe Contract Amount: $3,949,518 Duration: 12 months Scope: 30,500 LF of waterline installation (6"-12") 279 water service installations 7335 SY of asphalt removal/replacement 8300 SF of concrete removal/replacement 1900 LF of...

read more

Loop 303

Role: Sub Contractor Contract Amount: $1,853,219 Duration: 18 months Scope: 385 LF of waterline installation (12"-24") 2861 LF of sewer line installation (8"-30") 4 sewer manhole installations 1071 LF of sewer line removal 4980 LF of storm drain installation (18"-90")...

read more

Antelope Peak

Role: Prime Contractor Owner: Antelope Peak Domestic Water Improvement District Contract Amount: $401,142 Duration: 3 months Scope: 12,282 LF of waterline installation (4"-8") 24 water service...

read more