Miami : Phase 2 Wastewater Collection

Miami : Phase 2 Wastewater Collection

Role: Prime Contractor
Owner: Town of Miami
Contract Amount: $4,714,244
Duration: 7 months
Scope: 21,200 LF of sewer installation (8″-16″)
414 LF of jack & bore under US-60 and UPRR highway
239 sewer service installations
112 sewer manhole installations
2,082 LF of existing pipe rehab (CIPP)
4,406 SY of asphalt removal/replacement
707 SY of PCCP removal/replacement
Plevna, MT Waterline

Plevna, MT Waterline

Role: Prime Contractor
Owner: Town of Plevna
Contract Amount: $2,059,430
Duration: 5 months
Scope: 14,373 LF of waterline installation (6″)
582 LF of jack & bore under Highway 12
102 water service installations
890 SY of asphalt removal/replacement
17,240 SY of gravel restoration
Buckeye Reclaimed Waterline

Buckeye Reclaimed Waterline

Role: Subcontractor
Contract Amount: $1,625,879
Duration: 6 months
Scope: 18,775 LF of waterline installation (2″-12″)
  Site grading for water tanks
  1274 SY of asphalt removal/replacement
  3919 SF of concrete removal/replacement
   
   
Marana – Tangerine Sewer Conveyance System

Marana – Tangerine Sewer Conveyance System

Role: Prime Contractor
Owner: Town of Marana
Contract Amount: $2,095,288
Duration: 6 months
Scope: 18,170 LF of sewer line installation (15″-18″)
45 sewer manhole installations
7 CMID irrigation canal improvements
862 SY of asphalt removal/replacement
1890 SF of concrete removal/replacement
32,085 SY of ABC service road placement
Yuma P-535 Hangar

Yuma P-535 Hangar

Role: Subcontractor
Contract Amount: $1,290,407
Duration: 27 months
Scope: 1054 LF of waterline installation (3″-12″)
1422 LF of sewer line installation (4″-18″)
12 sewer manhole installations
1 lift station installation
1158 LF of storm drain installation (8″-24″)
29 Storm drain inlet & junction box installations